Beznau nuclear power plant: Unit 1 back on grid after scheduled outage

22.05.2020 – The Beznau nuclear power plant (KKB) has completed refurbishment work on Unit 1 and reconnected the reactor to the grid today following the approval of the Swiss Federal Nuclear Safety Inspectorate (ENSI). It was possible to complete the work on schedule despite all the corona-related restrictions and additional efforts. 

The focus of refurbishment comprised maintenance work, recurring tests and inspections. In addition, integral system tests were carried out as usual. Of the 121 fuel assemblies, 20 were replaced with new elements and installed in the reactor core.

As usual during a restart, KKB will also conduct various, additional safety tests on Unit 1 and gradually take up full-load operation. The plant will be back to full load in three days.

During refurbishment the approx. 460 employees at KKB were supported by some 400 external specialists from the region, as well as from Switzerland and abroad. KKB implemented strict measures to prevent the spread of the corona-virus and to protect its own and external staff. Entrance checkpoints, strict adherence to hygiene and distancing rules, health check-ups, quarantine in suspected cases, split operation and home office proved to be effective. No corona-virus infections occurred.

At times, visible steam will be emitted from the non-nuclear section of the plant during the restart. This does not pose any danger to human beings or the environment.

All work was supervised by the Federal Nuclear Safety Inspectorate ENSI.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Company 28.03.2024

Strengthening security of supply: Axpo is giving a clear Yes to the new electricity law, assessing the potential of operating Beznau for longer, and is prepared to construct a reserve power plant

Switzerland needs more electricity to achieve its climate goals. In order for the expansion of renewable energies to become a reality, we need a clear Yes to the draft of the new electricity law on 9 June. To further strengthen security of supply, Axpo has decided to clarify the technical feasibility of operating the Beznau nuclear power plant beyond 60 years. Axpo has also responded to the federal government’s tender (which ends today) and submitted a project for a reserve power plant for emergencies.

Read more

Hydropower 14.03.2024

KLL: Successful financial year

The shareholders of Kraftwerke Linth-Limmern AG (KLL) approved the report and annual financial statements for the 2022/23 financial year at their Annual General Meeting. KLL once again made a substantial contribution to Switzerland's electricity supply in the reporting period.

Read more

Hydropower 14.03.2024

KSL: Significantly more electricity produced

The shareholders of Kraftwerke Sarganserland AG (KSL) approved the annual financial statements and report for the 2022/23 financial year at their Annual General Meeting in Tierfed. Electricity production in the reporting year was significantly higher than the previous year and also above the long-term average.

Read more