High earthquake protection of Beznau NPP confirmed

The Swiss Federal Nuclear Safety Inspectorate ENSI has published its report on the assembly deviation on two of six emergency diesel generators at the Beznau nuclear power plant (KKB). ENSI concludes that KKB was safe and protected against earthquakes despite the assembly deviation.

As a consequence of Fukushima, ENSI increased the earthquake protection requirements for all Swiss nuclear power plants in 2012. At that time, KKB provided the necessary verifications with a positive result. In 2020, however, the assembly deviations on the emergency diesels were discovered. As a result, it only became clear in retrospect that the formal requirements had not been fully met in the event of an earthquake, which is to be expected only once every 10,000 years. This resulted in a formal deviation during two months (April and May 2012). With the commissioning of two retrofitted diesel generators in June 2012, the requirements were met again according to the authority.

Thanks to various retrofits and other measures, ENSI certifies that the KKB has a very high level of earthquake safety. Over the past decades, Axpo has invested around CHF 2.5 billion in the reliability and safety of the plant. During the months of April and May 2012, the level of earthquake protection was the same as in the months and years before.

In the meantime, KKB has analysed the reasons for the non-detection of the assembly deviation and various measures are being implemented. For example, additional checks are being carried out on ongoing projects to determine whether the components supplied correspond to the design. In addition, existing processes are being analysed and adjusted if necessary.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

International business 08.12.2023

Axpo, Egmont, and Soltech sign PPA for new solar plant in Sweden

The construction of a new solar plant in southern Sweden is the result of a unique collaboration between energy company Axpo, media group Egmont, and solar energy company Soltech Energy Solutions. The solar plant will be constructed by Soltech Energy Solutions and Axpo will manage the project’s long-term risks and the supply of solar power to the grid. The solar energy will then be traded through a power purchase agreement (PPA) and cover half of Egmont’s electricity consumption in Sweden and Norway with renewable electricity.

Read more

Renewable energy 07.12.2023

Business growth prompts Axpo office move in Vaasa

Axpo is moving into new offices in the Espen shopping centre in Vaasa this December, it was announced today. The decision to relocate was made as expanding employee numbers exceeded the capacity of Axpo’s current accommodation.

Read more

International business 06.12.2023

Axpo and Messer sign PPA for solar power from Südwerk

Axpo and German industrial gas specialist Messer have concluded a long-term power purchase agreement (PPA), it was announced today. From 1 January 2024, Axpo will supply two Messer facilities in Germany with electricity produced by Südwerk solar plants based in Bavaria.

Read more