Beznau nuclear power plant: Fuel element replacement in Unit 2 completed

18.8.2020 - Unit 2 of the Beznau nuclear power plant (KKB) went back on grid yesterday evening. During the work performed over a two-week period, one sixth of the fuel elements were replaced on an alternating basis. With the completion of reactor core reloading, the plant is now ready for the next operating period.

Unit 2 of the Beznau nuclear power plant was taken off grid on 4 August 2020 for scheduled refuelling. Over the last two weeks, 20 of the 121 fuel elements were replaced and installed in the reactor. In addition, recurring inspection work, integral system tests and scheduled work on individual plant components were carried out. 

Following the approval of the Federal Nuclear Safety Inspectorate ENSI, Unit 2 began gradually taking up full power operation. The plant will be back to full load in about two days.

At times, steam will be visible above the powerhouse during restart. This does not pose any danger to human beings or the environment.

 

Additional information

Axpo Holding AG, Corporate Communications 

T 0800 44 11 00 (Switzerland) | T +41 56 200 41 10 (international), medien@axpo.com

 

About Axpo:

Axpo is Switzerland's largest producer of renewable energy and an international leader in energy trading and the marketing of solar and wind power. 5000 employees combine experience and expertise with a passion for innovation. Axpo develops innovative energy solutions based on state-of-the-art technologies for its customers in over 30 countries in Europe and the USA.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Company 18.12.2015

Axpo achieves good operating result - Heavy loss caused by write-downs

Read more

International business 02.06.2016

Large volume order for Axpo in Germany

Read more

Company 22.01.2016

Axpo Holding AG: Carmen Walker Späh appointed to the Board of Directors

Read more