High earthquake protection of Beznau NPP confirmed

The Swiss Federal Nuclear Safety Inspectorate ENSI has published its report on the assembly deviation on two of six emergency diesel generators at the Beznau nuclear power plant (KKB). ENSI concludes that KKB was safe and protected against earthquakes despite the assembly deviation.

As a consequence of Fukushima, ENSI increased the earthquake protection requirements for all Swiss nuclear power plants in 2012. At that time, KKB provided the necessary verifications with a positive result. In 2020, however, the assembly deviations on the emergency diesels were discovered. As a result, it only became clear in retrospect that the formal requirements had not been fully met in the event of an earthquake, which is to be expected only once every 10,000 years. This resulted in a formal deviation during two months (April and May 2012). With the commissioning of two retrofitted diesel generators in June 2012, the requirements were met again according to the authority.

Thanks to various retrofits and other measures, ENSI certifies that the KKB has a very high level of earthquake safety. Over the past decades, Axpo has invested around CHF 2.5 billion in the reliability and safety of the plant. During the months of April and May 2012, the level of earthquake protection was the same as in the months and years before.

In the meantime, KKB has analysed the reasons for the non-detection of the assembly deviation and various measures are being implemented. For example, additional checks are being carried out on ongoing projects to determine whether the components supplied correspond to the design. In addition, existing processes are being analysed and adjusted if necessary.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Company 28.03.2024

Strengthening security of supply: Axpo is giving a clear Yes to the new electricity law, assessing the potential of operating Beznau for longer, and is prepared to construct a reserve power plant

Switzerland needs more electricity to achieve its climate goals. In order for the expansion of renewable energies to become a reality, we need a clear Yes to the draft of the new electricity law on 9 June. To further strengthen security of supply, Axpo has decided to clarify the technical feasibility of operating the Beznau nuclear power plant beyond 60 years. Axpo has also responded to the federal government’s tender (which ends today) and submitted a project for a reserve power plant for emergencies.

Read more

Solar energy 13.03.2024

Axpo discontinues planned alpine solar project in Glarus Süd

Following extensive investigations, Axpo has decided to discontinue its planned solar project in Glarus Süd. The reasons behind this decision are natural hazards, limited environmental compatibility and low energy yield. Axpo and the municipality of Glarus Süd regret this decision. Axpo will continue to invest in sustainable forms of energy and drive its Alpine projects forward.

Read more

International business 08.03.2024

Axpo and Jabil extend energy partnership in Hungary

Axpo and Jabil, a leading global electronics manufacturer headquartered in the United States, have renewed their long-term partnership in Hungary with a renewable energy corporate power purchase agreement (cPPA), it was announced today. The seven-year deal covers Jabil’s entire energy consumption in Hungary at two locations, marking an important advance towards the company’s environmental, social and corporate governance (ESG) goals.

Read more