Beznau nuclear power plant: Start of refueling in Unit 2

4.8.2020 - Unit 2 of the Beznau nuclear power plant (KKB) was taken off grid today, Tuesday, as planned in order to carry out refuelling. After reactor reloading, the plant will be ready for the next operating cycle.

The shutdown of Unit 2 marks the end of the production cycle that began on 20 September 2019. Since then, KKB 2 reliably produced about 2.9 billion kilowatt hours of electricity without interruption. This correspondsto the annual power consumption of about 600,000 households in Switzerland.

During the shutdown that will last about two weeks, 20 of the 121 fuel elements will be replaced and installedin the reactor core. In addition, recurring inspection work and integral system tests will be performed.

During the shutdown, steam from the non-nuclear section will be visible above the powerhouse. This does not pose any danger to human beings or the environment.

During refuelling, the approx. 460 KKB employees will be supported by some 120 external experts.

The measures instituted in spring to prevent the spread of the corona-virus and to protect internal and external staff will continue to be closely observed.

Refuelling work is supervised by the Federal Nuclear Safety Inspectorate ENSI.

 

Additional information

Axpo Holding AG, Corporate Communications 

T 0800 44 11 00 (Switzerland) | T +41 56 200 41 10 (international), medien@axpo.com

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Company 22.08.2025

Gösgen Nuclear Plant restart delayed, negatively impacting Axpo earnings

The anticipated restart of the Gösgen Nuclear Power Plant (NPP) has been delayed by a further six months. This will negatively impact Axpo Group’s financial results.

Read more

Solar energy 21.08.2025

Alpine solar plant at Muttsee supports grid stability

Switzerland’s largest alpine solar installation will provide balancing energy to the national grid operator, Swissgrid, from August 2025. The 2.2 MW facility forms part of the pioneering PV4Balancing pilot project, contributing to grid stability by helping to balance fluctuations in supply and demand.

Read more

Wind power 18.08.2025

Leadership change at Axpo wind division

Katja Stommel, CEO of Axpo subsidiary Volkswind and Head of the Wind Division, will step down from her roles at her own request effective 1 November 2025. She will be succeeded by Klaus Heckenberger, most recently Managing Director at Eurowind Energy GmbH, who is an experienced executive in the wind energy sector.

Read more