25.11.2026 | Circular economy in the Zürcher Unterland

Turning green waste into new energy in Bachenbülach

What is left over in gardens and kitchens can help supply energy. In the municipality of Bachenbülach in the Zürcher Unterland region, a biogas plant processes organic waste into renewable gas and natural fertiliser. Axpo Biomasse AG plans to replace the existing biogas plant with a modern new facility.

A bag of grass clippings, a bucket of vegetable peelings, pruned branches: these organic residues contain energy and nutrients that can be reused. In Bachenbülach in the Zürcher Unterland, this process is set to become even more effective.

Axpo Biomasse AG plans to completely dismantle its existing anaerobic digestion plant in the industrial area and build a new facility on the same site. The new plant is expected to process around 30,000 tonnes of green waste and other organic waste from the Zürcher Unterland and Furttal regions each year, turning it into renewable gas and fertiliser.

From green waste to biogas and fertiliser

Before waste can be turned into energy, the incoming material needs to be prepared. It is shredded and screened in a reception and pre-treatment hall. Metals and other unsuitable materials are removed. The prepared green waste then enters a sealed vessel known as the digester.

This is where anaerobic digestion takes place: in the absence of oxygen, microorganisms break down part of the organic material. In Bachenbülach, this process is planned to take place at a temperature of around 55 degrees Celsius. It produces biogas and digestate. The digestion process also helps sanitise the material.

The biogas is cleaned and upgraded to biomethane. This can be fed into the local gas grid, replacing fossil natural gas. Based on current plans, the plant could theoretically supply an amount of energy equivalent to the needs of more than 3,000 medium-sized flats.

The remaining digestate is separated into solid and liquid fractions. The liquid fraction, known as press liquor, can be used as fertiliser in agriculture. The solid fraction is processed into fresh compost, which is also intended to be available to private individuals for use in their gardens.

This closes a regional loop: the energy contained in green waste can enter the gas grid, while valuable nutrients are returned to fields and gardens.

A new facility after more than 30 years

The existing plant was built in 1992 and expanded in 2003. After more than three decades, it has now reached the end of its technical service life. Axpo Biomasse AG therefore plans to completely dismantle it and build a new facility at the current site. The replacement plant is intended to bring operations into line with today’s legal and environmental requirements.

These include safe storage of liquid digestate, the capture and use for energy of any methane released during storage, and improved quality of the natural fertiliser produced. An effective exhaust air treatment system is intended to treat contaminated air and minimise odour emissions. Water on the site will also be collected and drained separately according to its level of contamination.

At the same time, annual processing capacity is set to increase from around 20,000 to 30,000 tonnes of organic waste. This requires more space and new infrastructure. Plans include a reception and pre-treatment hall and separate storage areas for incoming green waste and the digestate remaining after digestion. A large tank is planned to ensure that liquid digestate is stored in accordance with regulations.

The additional infrastructure will slightly increase the operational footprint. Axpo Biomasse AG intends to build and operate the new facility itself.

Permanently removing CO₂ from the atmosphere

Upgrading biogas produces biogenic CO₂, originating from plant material. The project includes plans to capture and liquefy this CO₂ so that it can be used later. The liquefied CO₂ could, for example, be used in the production of certain materials. It would then be permanently bound within the material rather than released into the atmosphere. In this way, biogenic CO₂ could be stored for the long term and removed from the atmosphere.

Whether this use is possible depends on finding suitable customers for the captured CO₂.

The first steps towards the new facility have been taken

The building permit application for the new plant has been submitted and will be made available for public inspection. When construction can begin depends on the permitting process. Based on the current planning status, construction is expected to start no earlier than the second quarter of 2027.

Bachenbülach is part of a larger biomass network: Axpo Biomasse AG operates 15 anaerobic digestion plants and nine composting sites. Together, these sites process around 340,000 tonnes of biomass each year.

More articles for you

Show all

Sustainability

Tracking eels as they approach Schaffhausen hydropower plant

Downstream fish passage at hydropower plants

Read more

Energy market

European energy prices head into winter at post-2022 highs

European Energy Markets Monthly, November 2026

Read more

Energy market

Winter pressure builds across European energy markets

European Energy Markets Monthly, October 2026

Read more

Sustainability

How biochar can help protect the climate

Axpo enters the growing biochar market

Read more