Unit 2 of the Beznau nuclear power plant back on grid

07.08.2017 - Unit 2 of the Beznau nuclear power plant (KKB) went back on grid this morning, 7 August 2017, on the approval of the Federal Nuclear Safety Inspectorate ENSI.

The repairs on a 220-kV transformer cable in the non-nuclear section of the plant have been successfully completed. A reserve cable that was already installed for such cases was connected to the transformer, tested and put into operation.

The plant will now be gradually brought to full load. At times, steam from the non-nuclear section of the power plant will be visible. This does not pose any danger to human beings or the environment.

Axpo Holding AG

Corporate Communications

medien@axpo.com

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Ad hoc announcement 19.01.2024

Axpo Holding AG General Meeting – Shareholders forego a dividend

Read more

Ad hoc announcement 08.12.2022

A year marked by unprecedented turmoil on energy markets

Read more

Ad hoc announcement 11.05.2022

Axpo issues EUR 600 million sustainability-linked Schuldschein loan

Read more