Beznau nuclear power plant: emergency shutdown in unit 1

19.09.2025 – Due to the failure of an extra-high voltage line in the Swissgrid network, an emergency shutdown in KKB 1 occurred yesterday. The plant was in a safe condition at all times.

On Thursday, a high-voltage power line connected to the Beznau nuclear power plant failed. As a result, Unit 1 of the Beznau nuclear power plant (KKB) shut down automatically. This led to visible steam escaping above the plant's machine room in the non-nuclear part of the facility.

The power plant was in a safe condition at all times. The regulatory authority ENSI and other authorities were informed in accordance with regulations.

Technical investigations are currently underway. The date for restarting KKB1 will be determined in consultation with ENSI.

There is no danger to the population or the environment.

Axpo Holding AG

Corporate Communications

[email protected]

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Nuclear energy 19.05.2026

Beznau nuclear power plant: Unit 1 back on grid after revision

Read more

Hydropower 12.05.2026

Islas Regulating Reservoir: Main Renovation Work begins in June

Read more

Solar energy 08.05.2026

Axpo inaugurated 200 MWp solar complex in Spain

Read more