KKB: annual overhaul in block 1 completed

Beznau nuclear power plant (KKB) has completed work on the overhaul of block 1 and reconnected it to the grid following approval by the Swiss Federal Nuclear Safety Inspectorate (ENSI).

The overhaul focused on comprehensive maintenance work, inspections and commissioning of new systems. Integral system tests were also carried out, as usual. Out of 121 fuel elements, 16 were replaced.

The examination of the reactor pressure vessel ordered by ENSI in 2018 was also successfully carried out. This examination revealed no changes since the production-related aluminium oxide inclusions were noted in 2015. This once again confirmed the analysis and findings of the safety case in 2018.

The employees of the KKB, around 500 in total, received support from several hundred external experts from the region, Switzerland and abroad.

Block 1 will now gradually return to normal operations and will be at full capacity in two or three days. As the plant powers up, steam will be visible above the machine hall (non-nuclear part of the plant). There is no danger to people or the environment.

The overhaul was carried out under the supervision of ENSI.

Axpo Holding AG

Corporate Communications

[email protected]

T 0800 44 11 00 (Schweiz) 
T +41 56 200 41 10 (International)

(08.00 - 17.30)

More media releases

Show all

Hydropower 16.01.2026

Green light for new Mapragg doping power plant

Read more

Grids 15.01.2026

Relocation of underground cable to reinforce the electricity supply in the municipality of Glarus

Read more

Renewable energy 18.12.2025

Limmern pumped storage power plant: first electricity supplied to the Swiss grid ten years ago

Read more